Below are some of the directional boring and horizontal directional drilling (HDD)  projects we have completed over the last several years.

Holly Cushing Connect Project

Time Period: February 2021 - June 2021
Location: Cushing to Tulsa, Oklahoma
Owner of Project: Holly Energy Partners
Description of Project: 

  • 75 Bores/HDDs of 16" steel
  • From 80' to 897' in length
  • Approximately 16,000 linear feet of drilling
Atmos Line K5-1 West Project

Time Period: October 2020 - December 2020
Location: Walnut Springs to Iredell, Texas
Owner of Project: Atmos Energy
Description of Project: 

  • 17 Bores/HDDs of 12" steel
  • From 130' to 1,972' in length
  • Approximately 12,000 linear feet of drilling
ETC Lone Star Express Project

Time Period: December 2019 - March 2020
Location: Sweetwater to Abilene, Texas
Owner of Project: ETC
Description of Project: 

  • 75 Bores/HDDs of 24' steel
  • From 80' to 1,125' in length
  • Approximately 14,000 linear feet of drilling
Plains All-American Midland to Colorado City Loop Project

Time Period: May 2018 - July 2018
Location: Midland to Colorado City, Texas
Owner of Project: Plains All-American
Description of Project: 

  • 39 Bores/HDDs of 24" steel
  • From 40' to 1,377 linear feet
  • Approximately 14,000 linear feet of drilling
DCP Red Bluff Loop Project

Time Period: February 2018 - June 2018
Location: Orla to Odessa, Texas
Owner of Project: DCP
Description of Project: 

  • 52 Bores/HDDs of 20" steel
  • From 63' to 1,355' in length
  • Approximately 13,500 linear feet of drilling
Plains All-American Diamond Project

Time Period: February 2017 - July 2017
Location: Cushing to Cameron, Oklahoma
Owner of Project: Plains All-American
Description of Project: 

  • 11 HDDs of 20" steel
  • From 800' to 3,015' in length
  • Approximately 14,700 linear feet of drilling
Atmos Line Y Phase 2 Project

Time Period: October 2015 - August 2016
Location: Forney, Texas
Owner of Project: Atmos Energy
Description of Project: 

  • 43 Bores/HDDs of 30" steel
  • From 135' to 2,600' in length
  • Approximately 25,000 linear feet of drilling
Atmos Line Y Phase 1 Project

Time Period: July 2015 - October 2015
Location: Athens, Texas
Owner of Project: Atmos Energy
Description of Project: 

  • 26 Bores/HDDs of 30" steel
  • From 120' to 1,783' in length
  • Approximately 15,000 linear feet of drilling
XTO/Barnett Gathering Project

Time Period: August 2014 - October 2014
Location: Fort Worth, Texas
Owner of Project: XTO/Barnett Gathering
Description of Project: 

  • 2 HDDs of 12" steel
  • 4,898' & 6,098' in length
  • 10,996 linear feet of drilling
BridgeTex/Magellan

Time Period: February 2014 - April 2014
Location: Gatesville, Texas
Owner of Project: BridgeTex/Magellan
Description of Project: 

  • 4 HDDs of 20" steel
  • From 920' to 3,542' in length
  • 8,372 linear feet of drilling
Atmos Line WX Project

Time Period: February 2013 - December 2013
Location: Springtown to Godley, Texas
Owner of Project: Atmos Energy
Description of Project: 

  • 68 Bores/HDDs of 24" steel
  • From 70' to 1,900' in length
  • Approximately 42,000 linear feet of drilling
Atmos Line W Loop Project

Time Period: May 2012 - December 2012
Location: Boyd to Bowie, Texas
Owner of Project: Atmos Energy
Description of Project: 

  • 52 Bores/HDDs of 24" steel
  • From 80' to 2,000' in length
  • Approximately 32,000 linear feet of drilling
Location: Providence Village, Texas

Owner of Project: Atmos Energy
Length of HDD: 7,698' of 6" steel
Description of HDD: Completed an intersect drill under Lake Lewisville in clay, sand, sandstone, rock, and gravel.

Location: Fort Worth, Texas

Owner of Project: XTO/Barnett Gathering
Length of HDD: 5,360' of 8" steel
Description of HDD: Completed an intersect drill under the main runway at Sycamore Airport in rock.

Location: Palo Pinto County, Texas

Owner of Project: Palo Pinto Municipal Water District
Length of HDD: 1,250' of 36" HDPE
Description of HDD: Drilled the Brazos River in clay, sand, gravel, and rock.

Location: Louisiana

Owner of Project: Enterprise
Length of HDD: 5,700' of 6" steel
Description of HDD: Drilled wetlands in western part of the state in clay, sand, and sandy loam.

Location: Fort Worth, Texas

Owner of Project: XTO/Barnett Gathering
Length of HDD: 3,333' of 16" steel
Description of HDD: Drilled Main Street and Allen Street in rock.

Location: Gatesville, Texas

Owner of Project: BridgeTex/Magellan
Length of HDD: 3,542' of 20" steel
Description of HDD: Drilled environmentally sensitive Golden Cheek Warbler Area in rock.

Location: Colorado City, Texas

Owner of Project: Atmos Energy
Length of HDD: 1,500 of 36" steel
Description of HDD: Drilled the Colorado River in cobble, sand, and gravel.

Location: Fort Worth, Texas

Owner of Project: XTO/Barnett Gathering
Length of HDD: 6,089' of 12" steel
Description of HDD: Drilled I-20 in rock.

Location: Abilene, Texas

Owner of Project: Magellan
Length of HDD: 3,819' of 16" steel
Description of HDD: Drilled HWY 322 in rock.

Location: Bonham, Texas

Owner of Project: Atmos Energy
Length of HDD: 6,367' of 6" steel
Description of HDD: Drilled the Lower Bois D'Arc Creek Reservoir in clay, gravel, sand, and rock.